December 2025

  • Drop ceilings & lights installed.

  • Walls painted.

  • Shelving installed.


November 2025

  • Casework installed.

  • Drywall finished and beginning paint.

  • Interior windows installed.


October 2025

  • Demolition complete.

  • Overhead mechanical and electrical in progress.

  • Metal stud framing in progress.