June 2026 (Kitchen & Art Room)

  • Prime & 1st coat of paint complete, final coat will be applied early July

  • Resinous flooring in progress

  • Ceiling grid demo complete in Art Room, installation set for early July

  • Patch back concrete complete

August 2025


  • Construction is complete and classrooms are set up for the first day of school! Have a great year!

July 2025


  • Finishes are currently wrapping up.

  • Classrooms and corridors are receiving fresh paint, flooring, casework, and ceiling tiles.

  • The cafeteria flooring was also replaced.

June 2025


  • Demolition is ongoing in interior areas.

  • Painting has begun, with primer and first coat applied to walls.

  • Casework installation is in progress in classrooms and support spaces.