July 2026

  • Ceiling tile complete in all areas complete, LVT flooring in corridors have begun and is set to complete by mid-August

  • Casework installation complete in Areas A & B, Area C set to complete installation 7/31

  • Resinous flooring & wall topping in restrooms in progress, set to complete by end of the month


June 2026

  • All demolition/salvage complete

  • Metal Stud Framing in progress

  • Casework in progress