January 2026

  • Exterior framing and sheathing in progress

  • Exterior wall panels, roofing, and insulation in progress

  • Interior framing in progress


December 2025

  • Steel erection in progress.


November 2025

  • Steel delivered.

  • Detention pond grass is sprouting.


October 2025

  • Under-slab electrical and plumbing complete.

  • Slab-on-grade poured.

  • Site grading and seeding complete.


September 2025

  • Perimeter fencing complete.

  • Footings & stem wall in progress.

  • Slab-on-grade pours upcoming.


August 2025

  • Earthwork and site utilities are in progress.